Punctuality and Reliability Jan 07 - Feb 07


The punctuality and reliability figures for the end of December/January 2007 are as follows:

Punctuality: 88.2%
Reliability: 97.92%

The figures for February 2007 are as follows:

Punctuality: 86.7%
Reliability: 97.51%

Please find some of the problems affecting our services during this time:

· 5th Feb - There was a burst water main burst on Church Road, St George. As a result of repair work, the road was reduced to a single lane working.
· Work continues on the A420 showcase route.
· Delays as a result of junction improvement work - Bath Road at its junction with Callington Road.
· 11th Feb - 17th - Temporary traffic lights on Ashley Hill
· Various Dates - Cadogan Road closed until 22nd Feb.
· Various Dates - Ongoing roadworks on Stapleton Road.